Runway, INS HansaRenewal/ Resurfacing of Rigid Pavement of Runway at INS Hansa, Goa

Work has been tendered by HQ CE (Navy) Mumbai in the year 2013, under the aegis of Military Engineering Services. The cost of work is Rs. 24.088 crores. The scope of work comprises of removal of existing runway, WBM, WMM, Dense Bituminous Asphaltic Concrete, Dense Bituminous Macadam, Ready Mix Concrete in pavement of flexural strength 44kg/cm2. The work is to be executed, deploying ultra-modern machinery/ Tools and Plant. Strict quality control will be exercised by installing a fully equipped modern lab.

 

Client : HQ CE (Navy) Mumbai, MES
Start Date : 08 March 2013
Date of Completion 07 Sep 2014
Project Location  Goa
Work Status Completed